14 August 2000

The plan for today is to make sure the entire oven and the fill inside it are out and close both loci.

After poking around I noticed that the soil in the southern half of the trench was harder packed so I closed L2004 and opened up L2007 beneath it. I checked the oven, scraped around, and decided that I had found the bottom of it so I closed L2002 and L2006.

Now I'm having my workers take L2007 down by 15cm. I poked around the north half and noticed a new surface emerging in the northwest corner. I will therefore close L2005 and open up 2 loci beneath it- L2008, the new surface and L2009, the rest of the northern half.

After we pushed l2007down 15cm I didn't notice anything so i had them go down another 5cm. Meanwhile I scraped around L2008 and found that it extended farther than i originally thought.

Descriptive Attribute Value(s)
Date 2000-08-14
Year 2000
Has note The purpose of the daily journal was to record the activities taking place in a trench each day. This included which loci were excavated, how and why loci were excavated and the ongoing impressions of the relationships among loci. It should be noted that journals record the actions, impressions and ideas of trench supervisors during the excavations. They are not, therefore, the final interpretations or syntheses of the emerging data.
Dayplan-F-2-2000-08-14-A
Suggested Citation

Brian Bingham. (2012) "F-2-2000-08-14 from Asia/Turkey/Kenan Tepe/Area F/Trench 2/Locus 2002". In Kenan Tepe. Bradley Parker, Peter Cobb (Ed). Released: 2012-03-28. Open Context. <https://opencontext.org/documents/38a90616-cad2-49f1-8d3a-adfb96dc85ca> ARK (Archive): https://n2t.net/ark:/28722/k2dv1j455

Editorial Status
●●●●○
Part of Project
Copyright License

To the extent to which copyright applies, this content carries the above license. Follow the link to understand specific permissions and requirements.

Required Attribution: Citation and reference of URIs (hyperlinks)