July 15, 2001

We are taking photos and we will take elevations, and then we will continue to dig. I have removed the surface and now I am removing the whole L4003. I am doing it in 1m sections and my workers will dig it for at least 10cm, so the locus is 40xss03 and it will be 4005 after it will be cleaned.

We had to stop for breakfast. As I have thought it before, the mud brick pieces that I had left as L4000 seems to be a collapsed wall, and they are burned. We are sweeping and cleaning the mud bricks right at the moment with my workers.

The mud brick part was L4000, I was planning to dig the W part of the mud bricks, but as an accident I told my workers to cut off the mud bricks. When I recognized it they had dig for 10cm deep. I stopped them and wanted them to dig the W side of the mud bricks. I have changed to L4004.

Descriptive Attribute Value(s)
Date 2001-07-15
Year 2001
Has note The purpose of the daily journal was to record the activities taking place in a trench each day. This included which loci were excavated, how and why loci were excavated and the ongoing impressions of the relationships among loci. It should be noted that journals record the actions, impressions and ideas of trench supervisors during the excavations. They are not, therefore, the final interpretations or syntheses of the emerging data.
Dayplan-D-4-2001-07-15-A
Suggested Citation

Sibel Torpil. (2012) "D-4-2001-07-15 from Asia/Turkey/Kenan Tepe/Area D/Trench 4/Locus 4001". In Kenan Tepe. Bradley Parker, Peter Cobb (Ed). Released: 2012-03-28. Open Context. <https://opencontext.org/documents/c3a87513-6639-4b64-5755-f27f77cc5b5b> ARK (Archive): https://n2t.net/ark:/28722/k21z46881

Editorial Status
●●●●○
Part of Project
Copyright License

To the extent to which copyright applies, this content carries the above license. Follow the link to understand specific permissions and requirements.

Required Attribution: Citation and reference of URIs (hyperlinks)