June 19, 2007

Area D, Trench 6

Barish UZEL

    Today, we intensified L162 area and around the locus. Then, we saw the burned place (L162) is getting bigger under the L164 area. We also excavated other part of the trench with L163.

Descriptive Attribute Value(s)
Date 2007-06-19
Year 2007
Has note The purpose of the daily journal was to record the activities taking place in a trench each day. This included which loci were excavated, how and why loci were excavated and the ongoing impressions of the relationships among loci. It should be noted that journals record the actions, impressions and ideas of trench supervisors during the excavations. They are not, therefore, the final interpretations or syntheses of the emerging data.
Dayplan-D-6-2007-06-19-A
Suggested Citation

Catherine P. Foster. (2012) "D-6-2007-06-19 from Asia/Turkey/Kenan Tepe/Area D/Trench 6/Locus 159". In Kenan Tepe. Bradley Parker, Peter Cobb (Ed). Released: 2012-03-28. Open Context. <https://opencontext.org/documents/c05c8216-6e86-446b-a810-9b382c8b05f2> ARK (Archive): https://n2t.net/ark:/28722/k26974f35

Editorial Status
●●●●○
Part of Project
Copyright License

To the extent to which copyright applies, this content carries the above license. Follow the link to understand specific permissions and requirements.

Required Attribution: Citation and reference of URIs (hyperlinks)