Trench Layout
Trench Layout.
CB 54 was laid out using triangulation. A straight line was made with a tape between two nails previously placed by the site architect (50E, 49S and 55E, 49S), a nail was placed 4 meters east of 50E, 49S at 54E, 49S. Using this new line, 2 more points were placed through triangulation at 54E, 52S and 50E, 52S. These points were used to create straight lines and extend the southern baulk wall by 1 meter. The Coordinates of the trench, CB 54, are:
NW- 50E, 49S
NE- 54E, 49S
SE- 54E, 53S
SW- 50E, 53S.
Descriptive Attribute | Value(s) |
---|---|
Document Type | Trench Book Entry |
Trench Book Entry Date | 2012-06-18 |
Entry Year | 2012 |
Start Page | 15 |
End Page | 18 |
Title | Trench Layout |
Descriptive Attribute | Value(s) |
---|---|
Is Part Of
Vocabulary: DCMI Metadata Terms (Dublin Core Terms) |
AJC III
Vocabulary: Murlo |
Suggested Citation
Andrew J. Carroll. (2017) "AJC III (2012-06-18):15-18; Trench Layout from Europe/Italy/Poggio Civitate/Civitate B/Civitate B 54/2012, ID:648". In Murlo. Anthony Tuck (Ed). Released: 2017-10-04. Open Context. <https://opencontext.org/documents/e88b9771-0e13-4a64-86b6-8a389116ce0a> ARK (Archive): https://n2t.net/ark:/28722/k2hd84726
Copyright License
To the extent to which copyright applies, this content
carries the above license. Follow the link to understand specific permissions
and requirements.
Required Attribution: Citation and reference of URIs (hyperlinks)